Asset Protection Permits, Crossovers and Footpaths: The Street Side of a Brighton Demolition

Most people planning a knockdown in Brighton know they need a demolition permit and Section 29A consent. Far fewer know that the council also has a say over the footpath, kerb, nature strip and street tree outside the house, and that getting this wrong is one of the easier ways to lose money on an otherwise straightforward demolition. This guide covers what Bayside City Council expects on the street side of the boundary, what it costs you if the footpath is damaged, and how to set the job up so the bond comes back.

What an asset protection permit is

Like most Melbourne councils, Bayside requires an asset protection permit before demolition or building works start on a property. The idea is simple. The footpath, kerb and channel, nature strip, drainage pits and street trees belong to council, and heavy machinery, trucks and skip bins routinely damage them. The permit records the condition of those assets before work begins, so that any damage afterwards can be attributed and repaired at the owner's cost rather than the ratepayer's.

In practice the permit involves an application, a fee, and usually a bond or security that council holds until the works are finished and a final inspection shows the assets are in the same condition as they were at the start. The amounts change over time and depend on the scale of the works, so check the current figures with council rather than relying on a number from a neighbour who built three years ago.

The permit is normally the owner's responsibility, not the demolisher's, although we will tell you when to apply and what to photograph. It also typically covers the whole project, so if your builder is starting straight after us, one permit held in the owner's name can run through from demolition to handover. Confirm that with your builder early, because two permits for one block is wasted money.

Photograph everything before the first truck arrives

The single most useful thing you can do is a thorough photographic record of the street frontage before any works begin. Walk the full width of the block and a few metres either side. Photograph the footpath slab by slab, the kerb and channel, the crossover, the nature strip, any drainage pit lids and the base of the street tree. Date the images. If there is already a cracked slab or a broken kerb, that is exactly what you want on record.

Council inspectors do their own pre-works inspection in most cases, but their photos protect council. Yours protect you. If a dispute arises about whether a crack was there beforehand, the owner with dated photographs usually wins it.

Crossovers, kerbs and getting machines onto the block

An excavator and a steady stream of trucks have to get from the road onto the site. On many Brighton and Hampton blocks the existing concrete crossover is narrow, old and not built for the weight. Driving a float or a loaded truck over an undersized crossover is a common way to crack it, and the same applies to mounting the kerb where there is no crossover at all.

There are a few ways to handle this. Where the crossover is sound and wide enough, we use it and protect the edges. Where it is not, a temporary crossover can be formed with steel plates or compacted crushed rock over the kerb, under a permit from council. And if the existing crossover is being replaced anyway as part of the rebuild, it is sometimes simplest to remove it during demolition and have the builder install the new one later, provided council agrees and the nature strip is protected in the meantime.

A new or relocated crossover needs its own vehicle crossing permit, and council sets the construction standard. That is generally the builder's scope, but it is worth deciding the location early because it affects where we bring machines in.

Skips, trucks and the road

Parking a skip bin, a crane or machinery on the road or nature strip usually requires a separate occupation permit from council, and in busy streets or near schools there may be conditions on timing. On a typical full house demolition we load directly into trucks rather than leaving bins on the street, which avoids most of this, but a partial demolition or strip-out with a long program may need a bin on the nature strip for a period. We arrange the permit where that applies and note it in the quote.

Street trees and nature strips

Street trees in Bayside are protected council assets, and the rules on working near them are stricter than many people expect. A tree protection zone extends out from the trunk, and parking machinery, stockpiling material or trenching inside it can attract a penalty quite apart from any damage. Where a street tree sits close to the crossover we fence or plate the root zone and route trucks around it. The nature strip itself should be left as grass, not as compacted clay, and reinstating it is part of leaving the job finished.

Getting the bond back

The bond is refunded after a final inspection, which usually happens once the whole project is complete rather than at the end of demolition. If damage is found, council either deducts the repair cost or requires you to reinstate the asset to its standard. The common failures are cracked footpath slabs from truck wheels, a broken kerb at the entry point, sunken nature strip where a machine sat for days, and a drainage pit lid broken by a wheel.

All of these are avoidable with plates, an agreed entry point and a crew that treats the street as part of the site. It is also why a demolition quote that assumes no protection at all can look cheaper than one that includes it. Our knockdown-rebuild site preparation pricing includes frontage protection as standard, and our permits and heritage approvals service will tell you which council permits apply to your address before anything is lodged.

What to do before you sign

Before you accept a quote for a full house demolition in Brighton, Brighton East, Hampton or Sandringham, ask three questions. Who is applying for the asset protection permit and when. How will machines enter the block and what protection will be in place. And who reinstates the nature strip and crossover if they are disturbed. Clear answers to those three save a surprising amount of money and argument at the end of the project.